New warehouse/office
  1. Springview Commerce Park, DeBary, Florida.
  2. Lot 11 Newtech Court. Site of new warehouse.
  3. Building pad started late October 2004.
  4. Another view of the building pad.
  5. Freshly-poured concrete. (12/27/04)
  6. Another view of the concrete slab. (12/27/04)
  7. View of the slab with Springview Commerce Dr. in the background. (12/27/04)
  8. The cement blocks have been delivered. (1/6/05)
  9. "The owner's takin' pictures so let's look like we're busy workin'." (1/6/05)
  10. My car at the entrance of 404 Newtech Ct. (1/7/05)
  11. ¾-view of the front of the building. (1/7/05)
  12. Inside of building looking towards the back wall. (1/7/05)
  13. Another inside view looking towards the unloading area. (1/7/05)
  14. Inside view from the back of the building (staging area). (1/10/05)
  15. Opposite inside view angle looking towards the staging area. (1/10/05)
  16. Frontal view of the building. Walls are 90% complete. (1/10/05)
  17. Close-up of the front and main entrance. (1/10/05)
  18. Rear view of the building. (1/12/05)
  19. Garage/service doors detail (staging area). (1/12/05)
  20. Rebar tying detail (required by code). (1/12/05)
  21. Backyard view. (1/12/05)
  22. Small window opening detail. (1/12/05)
  23. Lintel finished and hurricane straps in place. (1/19/05)
  24. Cement has been poured as required by code. (1/19/05)
  25. Hurricane straps from the inside. These wrap over the trusses to further secure them. (1/19/05)
  26. Materials for the inside walls. (1/19/05)
  27. Same stuff, different angle. Lots of 2x4s and other related materials. (1/19/05)
  28. Close-up of the construction permit showing inspections conducted. (1/19/05)
  29. The trusses for the roof have been delivered to the site. (1/22/05)
  30. Close-up of the trusses pack. Very foggy Saturday morning. (1/22/05)
  31. Trusses being lifted into place. (2/2/05)
  32. More of the same. (2/2/05)
  33. Same stuff, different angle. (2/2/05)
  34. Close-up of trusses being installed. (2/2/05)
  35. Inside of building. Wall footers in place. (2/2/05)
  36. Furring strips and lots of trusses. (2/2/05)
  37. Looking towards the offices, bathrooms, and kitchen area. (2/2/05)
  38. Staging area view. (2/2/05)
  39. Main lobby and office close-up. (2/2/05)
  40. This guy won't be smiling when they hand him the final bill. (2/2/2005)
  41. Richie (the builder) probably smiling because he knows how much he will charge. (2/2/05)
  42. Frontal view of building. (2/2/05)
  43. ¾ front view. (2/2/05)
  44. View from the main raod. The roofer has started installing the plywood. (2/3/05)
  45. ¾ front view. Windows have been installed. (2/3/05)
  46. Window detail. (2/3/05)
  47. Inside view showing some of the wall studs in place. (2/3/05)
  48. Same area from a different angle. (2/3/05)
  49. Sheila's office. (2/3/05)
  50. Loading/unloading area close-up. (2/3/05)
  51. ¾ front view with most of the roof done. (2/4/05)
  52. Inside of the building looking out. The water is from the rain we've been having lately. (2/4/05)
  53. Bathrooms and kitchen area. (2/4/05)
  54. Service door in front of building. This leads to the parking lot and dumpster area. (2/4/05)
  55. Rear view of the warehouse. Plywood platform still up. (2/4/05)
  56. Close-up view of the trusses and hurricane straps. (2/4/05)
  57. Main entrance detail. The roof above it will be gabled into the main one. (2/4/05)
  58. Another shot of the front of the warehouse. (2/4/05)
  59. Roof plywood is mostly done, except for the gable over the main entrance. (2/7/05)
  60. Main entrance detail. (2/7/05)
  61. Offices area. (2/7/05)
  62. Kitchen and staging area. (2/7/05)
  63. Utility room wall footers. (2/7/05)
  64. Entrance lobby (French door framing needs to be redone to accomodate 8-foot doors. (2/7/05)
  65. Storage room wall footers. (2/7/05)
  66. Most of the roof has been covered with black roofing paper. (2/8/05)
  67. Rough framing of the staging area. (2/8/05)
  68. Staging area detail. (2/8/05)
  69. Postage station knee-wall. (2/9/05)
  70. Storage room. (2/9/05)
  71. Air conditioner utility room. (2/9/05)
  72. Knee wall detail. (2/9/05)
  73. Storage room and office looking from staging area. (2/9/05)
  74. Postage station knee wall detail with warehouse are in the background. (2/9/05)
  75. Electrical work started. (2/10/05)
  76. Postage station knee wall electrical detail. (2/10/05)
  77. Kitchen/breakroom entry arch detail. (2/10/05)
  78. Air conditioning/heating duct work has also begun. (2/10/05)
  79. Lobby office electrical work detail. (2/10/05)
  80. Roof is now ready for shingles and some of the doors have been installed. (2/10/05)
  81. Air conditioning/heating duct installation continues. (2/12/05)
  82. AC electrical and feed lines. (2/12/05)
  83. AC parts. (2/12/05)
  84. Air handler box in utility room. (2/12/05)
  85. Another shot of the air handler box inside the utility room. (2/12/05)
  86. Air duct and vent in staging area. (2/13/05)
  87. Air duct junction detail. (2/13/05)
  88. Inside view of warehouse area. (2/13/05)
  89. Air conditioner unit main feed lines. (2/13/05)
  90. Shingles have been delivered to the site. (2/15/05)
  91. Installation of the metal "banding" frame already underway . (2/15/05)
  92. Banding frame detail. (2/15/05)
  93. Banding around one of the windows. This will be covered with stucco. (2/16/05)
  94. Entrance columns detail. (2/16/05)
  95. Staging area and side door entry. (2/16/05)
  96. Another view of the building with the shingles ready for installation. (2/16/05)
  97. "Scratch" stucco coat has been applied to the whole building. (2/17/05)
  98. The wall on the right shows the finish coat for contrast. (2/17/05)
  99. The right side as well as the rear of the building are done. Finish coats are still wet. (Note: there's no band on the back wall). (2/17/05)
  100. Window detail. Bands are finished smooth. The walls are textured. (2/17/05)
  101. Half done—half to go. (2/17/05)
  102. The stucco work is now finished. (2/19/05)
  103. Entry columns detail. (2/19/05)
  104. Exhaust fan installation detail in one of the restrooms. (2/19/05)
  105. Shingles are now being attached to the roof. (2/19/05)
  106. Back and left area of the roof with all the shingles installed. (2/19/05)
  107. Busy Monday! Roofers, dry wall delivery guys, electrician, air conditioning workers, and parking lot surveyers and crew. (2/21/05)
  108. Built-in crane speeds up dry wall delivery. (2/21/05)
  109. Crane in action while it unloads a batch of drywall. The crane is remote-controlled. (2/21/05)
  110. Roofers hard at work in order to finish installing the shingles. (2/21/05)
  111. The crane allows these guys to bring the dry wall panels pretty close to the unloading point. (2/21/05)
  112. Once inside, they move it around on these carts. (2/21/05)
  113. Dry wall delivery truck. (2/21/05)
  114. Parking lot work begins. (2/22/05)
  115. Front parking area and unloading ramp. (2/22/05)
  116. ¾ front view. (2/22/05)
  117. More parking lot prep work. (2/23/05)
  118. Clearing on the right side is the dumpster area. (2/23/05)
  119. Back yard has been partially filled in and leveled. (2/23/05)
  120. Clay is used to help harden the parking lot surface. (2/24/05)
  121. The areas shown without clay will be planting beds. (2/24/05)
  122. Electric meter, phone, and cable conduits. (2/24/05)
  123. Drywall "waits" for the framing inspection. (2/24/05)
  124. The loading dock/staging area garage door has been installed. (2/25/05)
  125. East side of the building painted. (3/2/05)
  126. Rear of the building freshly painted. (3/2/05)
  127. Parking lot ready for forms. (3/2/05)
  128. Front of the building painted. (3/2/05)
  129. Front of the building and some of the parking lot detail. (3/2/05)
  130. Parking lot looking East towards Newtech Court. (3/2/05)
  131. Dumpster area formed and ready for concrete. (3/2/05)
  132. Painters and aluminum trim installer at work. (3/3/05)
  133. East side of building detail. (3/3/05)
  134. Beautiful (albeit chilly) morning with the exterior painting done. (3/4/05)
  135. Ready for parking lot cement. (3/4/05)
  136. Parking lot paving started at 5am. By 8am this is how the site looked. (3/5/05)
  137. One of the cement trucks delivering concrete mix. (3/5/05)
  138. Loading dock area work detail. (3/5/05)
  139. Approx. half of the main parking lot poured. (3/5/05)
  140. Main entrance walkways poured. (3/5/05)
  141. Main parking lot view. (3/5/05)
  142. Main parking lot looking south. (3/5/05)
  143. Walkway. (3/5/05)
  144. More of the same. (3/5/05)
  145. There were 5 trucks like this one delivering the concrete mix. (3/5/05)
  146. Once the walkways were poured, work continued on the loading dock area apron. (3/5/05)
  147. More of the same. (3/5/05)
  148. And more concrete mix poured. (3/5/05)
  149. After the parking lot was poured, the entrance driveway was prepped for inspection on Monday. (3/5/05)
  150. After the inspection, the concrete will be poured on this area. (3/5/05)
  151. Loading dock area being "troweled" by machine. (3/5/05)
  152. At around 4:30pm, the concrete guy cut grooves on the pavement to prevent cracking. (3/5/05)
  153. Parking area view from behind the dumpster pad. (3/5/05)
  154. Main entrance detail. (3/5/05)
  155. Air conditioner pads. (3/5/05)
  156. View from the loading dock. (3/5/05)
  157. Main parking lot view. (3/5/05)
  158. Water well boring rig. (3/9/05)
  159. Well boring detail. (3/9/05)
  160. Well pump and valve. (3/10/05)
  161. Now that the driveway and parking lot are done, one is able to drive to the parking area. (3/10/05)
  162. Driveway off Newtech Court. (3/10/05)
  163. Main electrical panel. (3/10/05)
  164. The parking lot curbs have been poured and they are covered due to rainy weather. (3/15/05)
  165. Another view of the parking area. (3/15/05)
  166. Insulation work has been started. (3/16/05)
  167. Main entrance viewed from the warehouse. (3/16/05)
  168. Kitchen and staging area. (3/16/05)
  169. Staging area view from outside of the building. (3/16/05)
  170. Sheila's office, bathrooms, and kitchen. (3/16/05)
  171. Parking lot showing curbs and one of the planting beds. (3/18/05)
  172. Drywall work started. Inside one of the restrooms. (3/21/05)
  173. Kitchen partially drywalled. (3/21/05)
  174. Ceiling work started over storage room. (3/21/05)
  175. Postage area kneewall drywalled. (3/21/05)
  176. Warehouse area looking towards offices and storage room. (3/22/05)
  177. Luis' office and computer room. (3/22/05)
  178. One of the restrooms. (3/22/05)
  179. Warehouse area. Ceiling almost done. (3/22/05)
  180. Offices and entrance. (3/22/05)
  181. Another view of the warehouse ceiling. (3/22/05)
  182. Riverside Bank sign. (3/22/05)
  183. Walls have been taped and the first coat of joint compound has been applied. (3/26/05)
  184. Offices and postage station wall. (3/26/05)
  185. Staging area and air-conditioner room. (3/26/05)
  186. Postage station and kitchen doorway in the background. (3/26/05)
  187. Warehouse area. (3/26/05)
  188. Storage room. (3/26/05)
  189. Slab had to be cut out since the floor outlets were positioned in the wrong spot. Sheila's office. (3/26/05)
  190. Same deal in Luis' office. Holes will be filled with concrete in a couple of days. (3/26/05)
  191. Phone, cable and computer network cabling in the computer room. (3/26/05)
  192. Planting bed showing some of the irrigation system preparations. (3/28/05)
  193. Sidewalk has been boarded and it's ready for concrete. (3/29/05)
  194. Small sidewalk and one of the irrigation system trenches. (3/29/05)
  195. Irrigation system pipe detail. (3/29/05)
  196. Irrigation system ditch west side of the building. (3/29/05)
  197. Sheila's office window detail. (3/30/05)
  198. Kitchen doorway arch. Walls have been sanded smooth and are ready for the texture coat to be applied. (3/30/05)
  199. Staging area side door. (3/30/05)
  200. Mens bathroom and closet in background. (3/30/05)
  201. Postage station wall needs to be leveled. (3/30/05)
  202. Staging area roll-up door. (3/30/05)
  203. Warehouse view. (3/30/05)
  204. Entrance lobby. (3/30/05)
  205. Wall texture has been applied and the inside of the building is ready for paint. (3/31/05)
  206. Ceiling knock-down texture. (3/31/05)
  207. Floor outlet holes have been filled with concrete. (3/31/05)
  208. In Sheila's office the original outlet holes will have caps to allow for access if needed. (3/31/05)
  209. Dumpster fence posts in place. (3/31/05)
  210. The landscape company pre-dug the planting holes for the trees. (3/31/05)
  211. Tree planting holes in the rear of the building. (3/31/05)
  212. Planting begins. (4/1/05)
  213. Landsape work in the front of the building. (4/1/05)
  214. Warehouse area ready for paint and flooring. (4/1/05)
  215. Postage station wall area. (4/1/05)
  216. Tree planting and testing the irrigation system. (4/2/05)
  217. Front view of the building. (4/2/05)
  218. Same but different angle. (4/2/05)
  219. I believe these are Crepe Myrtle trees. Not sure what color they are. (4/2/05)
  220. Inside walls have been painted a shade of beige. (4/2/05)
  221. Postage station. Note: the light was not helpful when I took the photo, hence the splotches. (4/2/05)
  222. Staging area and air-conditioner room. (4/2/05)
  223. Postage station and kitchen doorway with one office and restrooms in the background. (4/2/05)
  224. Oak trees in backyard. Grass will be installed next week. (4/2/05)
  225. Rear view of the building. (4/2/05)
  226. Entrance planting area. (4/2/05)
  227. Planting beds in front of the building. (4/2/05)
  228. Flooring started in kitchen. (4/4/05)
  229. Flooring detail in women's restroom. (4/4/05)
  230. Flooring in men's restroom. (4/4/05)
  231. Richie (the builder) standing behind the postage station wall. (4/4/05)
  232. Exit signs have been installed. (4/4/05)
  233. Exit signs above main exits also have emergency lights. (4/4/05)
  234. View of the staging area. The door will be installed soon. (4/4/05)
  235. Postage station cabinets being installed. (4/5/05)
  236. More of the same. (4/5/05)
  237. Kitchen cabinetry installation. (4/5/05)
  238. Kitchen counter top. (4/5/05)
  239. Grass being laid behind the building. (4/5/05)
  240. Floor prep work in Sheila's office before laying the tile. (4/5/05)
  241. Top shelf of the postage station. (4/5/05)
  242. Applying Mastic adhesive for the tile work. (4/5/05)
  243. Tile work continues. (4/5/05)
  244. Kitchen cabinets again with above-fridge cabinet detail. (4/5/05)
  245. Kitchen sink has been installed. (4/5/05)
  246. Postage station almost done. (4/5/05)
  247. Men's restroom sink and light fixture detail. (4/5/05)
  248. Sheila's office flooring done. (4/5/05)
  249. Baseboards installed in Sheila's office. (4/6/05)
  250. VCT baseboards in kitchen. (4/6/05)
  251. Postage station finished. (4/6/05)
  252. French doors installed. (4/6/05)
  253. Entrance lobby/office with French doors and crown molding. (4/6/05)
  254. Grass area in one of the front planting beds. (4/6/05)
  255. Staging area access door installation. (4/6/05)
  256. ¾ front view of building. (4/6/05)
  257. West side of building. (4/6/05)
  258. Installation of one of the offices indoor windows. (4/6/05)
  259. Painting the parking lot stripes. (4/8/05)
  260. Prepping the handicapped area to be painted. (4/8/05)
  261. One of the air handlers. (4/8/05)
  262. Front doors have been delivered and they will be installed last. (4/8/05)
  263. Staging area floor has been tiled. (4/8/05)
  264. Handicapped parking space finished. (4/8/05)
  265. Warehouse ready for light fixtures to be installed. (4/11/05)
  266. Floor outlet installation detail. (4/11/05)
  267. Air conditioners. (4/11/05)
  268. Parking "bumpers" during their installation. (4/11/05)
  269. Front of building parking area. (4/11/05)
  270. Water heater and sink in one of the service rooms. (4/11/05)
  271. Power company checking lines. (4/11/05)
  272. Reflective cross-walk stripes have been installed. (4/11/05)
  273. Parking lot view. (4/11/05)
  274. Light fixture installation in the warehouse area is underway. (4/11/05)
  275. New light fixtures are working. (4/13/05)
  276. Front row of lights lit up. (4/13/05)
  277. French door has been painted. (4/13/05)
  278. One of the a/c thermostats. (4/13/05)
  279. George finishing up the dumpster area. (4/13/05)
  280. Front doors installed. (4/16/05)
  281. Luis' office floor waxed and polished. (4/16/05)
  282. Applying the urethane sealer/wax to the main warehouse area. (4/16/05)
  283. More of the same. (4/16/05)
  284. Storage room area. Wax brings out the tile color and detail. (4/16/05)
  285. Air conditioner room and staging area doors. Floor is ready to be buffed for max gloss. (4/16/05)
  286. New metal shelves. (4/19/05)
  287. Richie writing up a "to-do" list at the postage station desk. (4/19/05)
  288. Wide view of the warehouse area and shelving. Only 57 more units to go. (4/19/05)
  289. Kitchen lamp detail. (4/19/05)
  290. New refrigerator has been delivered and installed. (4/22/05)
  291. Phone and networking buses in the computer room. (4/22/05)
  292. Phone and computer bus detail. (4/22/05)
  293. More shelving. (4/23/05)
  294. Same stuff, different angle. (4/23/05)
  295. Shelving "Rivet-Lock" detail. (4/23/05)
  296. Assembling the packing table after leveling the base. (4/26/05)
  297. Packing table sections. (4/26/05)
  298. Packing table half mounted on its base. (4/26/05)
  299. Geri's office furniture assembly. (4/26/05)
  300. Cutting the base board so the desk can fit flush against the wall. (4/26/05)
  301. lnside of desk. Top area are cubby holes. (4/26/05)
  302. Packing table and bubble wrap dispensers in place. (4/26/05)
  303. Back to entrance office: Bob levels back of desk. (4/26/05)
  304. Securing backside of desk to the wall. (4/26/05)
  305. Packing table with both sides in place. (4/26/05)
  306. Desk and desktop in place. (4/26/05)
  307. Overall view of packing table. (4/26/05)
  308. Table top attached. (4/26/05)
  309. Bubble wrap dispenser. Doors will be installed later. (4/26/05)
  310. Packing table completed. The round hole is for the garbage container. (4/26/05)
  311. Vince assembling bookshelves. (4/26/05)
  312. Packing table, postage station and entrance office view. (4/26/05)
  313. Geri's desk completed. (4/26/05)
  314. Custom bubble wrap dispenser detail. (4/26/05)
  315. Makeshift desk in Luis' office. (5/1/05)
  316. Another angle of same. (5/1/05)
  317. Phone/Network panel. (5/1/05)
  318. Geri's desk. (5/1/05)
  319. Sheila's desk. (5/1/05)
  320. We're out of room . . . AGAIN! (Just kidding). (5/1/05)
  321. Some of this weekend's orders ready for picking. (5/1/05)
  322. Partial view of the warehouse. (5/1/05)
  323. Old plastic shelving will be phased-out eventually. (5/1/05)
  324. New shelving with some of the automotive manuals. (5/1/05)
  325. Backside of same. (5/1/05)
  326. Used book section. (5/1/05)
  327. Warehouse looking towards kitchen. (5/1/05)
  328. Temporary Haynes automotive section. (5/1/05)
  329. Extra computer terminal. (5/1/05)
  330. Kitchen. (5/1/05)
  331. Everyone pitched in to get me a present for my office. (5/16/05)
  332. Detail of the "globe" which is made out of metal. Looks fantastic. (5/16/05)
  333. Our new "toy." A Toyota Walkie-Stacker. This electric lift is smaller than a traditional fork-lift and a lot quieter. (5/17/05)
  334. Another picture of the unit. Very easy to operate too. (5/17/05)
Move to new warehouse
  1. The old postage station. (4/29/05)
  2. Old packing table. (4/29/05)
  3. Geri at her station. (4/29/05)
  4. Luis at his desk. (4/29/05)
  5. Sheila at the postage station. (4/29/05)
  6. Carmen and Devon. (4/29/05)
  7. Let's start packing some of this stuff. (4/29/05)
  8. Geri with the "boat section." (4/29/05)
  9. The old kitchen in unit 107. (4/29/05)
  10. Vince is ready to move. (4/29/05)
  11. Devon, Carmen and Vince. (4/29/05)
  12. Books in boxes everywhere. (4/29/05)
  13. Thank God for USPS tubs. (4/29/05)
  14. Still lots of books to pack. (4/29/05)
  15. Early start on moving day. (4/30/05)
  16. And this is what the old office looked after the move. (5/1/05)
  17. Unit 105 is ready for the new owners. (5/1/05)
  18. Richie, the builder, was there on moving day insuring everything was okay. (4/30/05)
  19. Richie testing the chair while Luis and John assemble Sheila's desk. (4/30/05)
  20. Now that's more like it. "Real" offices. (5/2/05)
  21. Sheila at her desk in her new office. (5/1/05)
  22. Geri trying to get her station ready for the workweek. (4/30/05)
  23. Some of the temporary shelving during the move. (4/30/05)
  24. Postage station, finally operational. (5/2/05)
  25. Some of the packages ready for shipping. (5/2/05)
  26. Geri's office. (5/2/05)
  27. Storage room and extra order-taking station. (5/2/05)
  28. Our new warehouse pretty packed already! (5/2/05)
Pickford Square office
  1. Pickford Square Plaza in Deltona, Florida. (January 2005)
  2. Order-taking station/kitchen (before we rented unit 107).
  3. Bookshelves looking towards the main entrance area.
  4. The original packing tables.
  5. Packing tables with part of the Clymer motorcycle manual section in the background.
  6. Postage station (originally Sheila's "office").
  7. Storage "closet".
  8. Luis' office (later it became Luis & Sheila's office and used manual storage).
  9. More shelves and mail tub storage area.